Schedule

On April 1, 2023, the appointed scientists began conducting the UFP exposure study. The planned duration of the study is 36 months. If the iterative process for generating a valid emissions data foundation takes longer than 6 months, the other steps in the work may be delayed by up to 6 months, and a new schedule with a maximum project duration of 42 months will be established.

Schedule of the exposure study